Production planning in Excel, and when a digital planning board works better

A production plan in Excel is a sheet with one row per order: which line it runs on, when it starts, how long it takes and when it is finished. For a few lines and a quiet week that works fine. Once rush orders, changeovers and progress from the floor come into play, the file falls behind and a digital planning board that the office and the floor both see live works better.

Updated October 7, 2026

What goes into a production plan in Excel

A useful plan answers three questions per line: what is running, when does it start and when is it finished. Put all orders in one table with a column for the line, so you can filter and sort per line.

The columns you need at a minimum:

  • Order number, item and customer, taken from the ERP
  • The line or machine the order runs on
  • The quantity and the speed of that line, for example bottles per hour
  • The changeover time in minutes to switch to this item
  • The start time and the calculated end time
  • The delivery date, so you can see which order is at risk of being late
  • A status: planned, running or done

An example: order PO-88213 on line 2

Order PO-88213 calls for 12,000 bottles. Line 2 fills 1,500 bottles per hour, so the order itself takes 8 hours. Before that, the line needs a 45 minute changeover. If the changeover starts on Monday at 06:00, the order is finished at 14:45.

In Excel, date and time together are one number, where 1 is a whole day. With the start in B2, the quantity in C2, the speed per hour in D2 and the changeover in minutes in E2, you calculate the end time in F2 with =B2+E2/1440+C2/D2/24. Format F2 as date and time.

The next order on the same line starts where the previous one ends: in B3 you enter =F2. If PO-88213 takes longer, the orders after it move along. With conditional formatting you colour the end time red as soon as it falls after the delivery date.

Where an Excel plan gets stuck

The arithmetic is rarely the problem. It goes wrong with everything that happens after the plan is made:

  • Inserting a rush order breaks the chain of formulas: the new row stands alone and the orders after it do not move
  • Shifts, breaks and the weekend are not in the formula, so on paper an order simply runs through the night
  • The changeover time depends on the previous product, but the sheet knows one fixed value per row
  • Whether materials arrive on time is not visible in the same sheet
  • What really happens on the floor only comes in when someone types it, often the next morning
  • Soon there are several versions: the planner works in one, the shift leader has a printout from yesterday
  • Every change then has to be passed on by hand to the warehouse, sales and the customer

What a digital planning board adds

A digital planning board shows the same orders as a timeline per line. You drag an order to a line and a time slot, and the orders after it move along on their own. A good planning board takes capacity, changeover times and materials into account.

The big difference from Excel is that the board works both ways. Orders come from the ERP, and progress comes from the line: counts from the machine or from the operator on a tablet. The office and the floor look at the same plan, which shows what is done and what is behind.

What you gain compared with the sheet:

  • One current version for the planner, the shift leader and the warehouse
  • A warning when an order does not fit or materials are missing
  • An end time that moves with what really happens on the line
  • On every change, a new pick list for the warehouse and a new date for sales straight away

When is Excel no longer enough?

Excel is a fine start, and for a small, stable operation it can be enough for a long time. It is time for something else if you recognise these signs:

  • The planner spends hours every day replanning
  • Rush orders come in every week
  • Lines wait for each other or share materials and people
  • The shift leader walks to the office to ask what to run next
  • Sales only hears about a delay when the customer calls
  • When the planner is ill, nobody knows how the file works

Frequently asked questions

How do I make a production plan in Excel?

Make one row per order with the line, quantity, speed, changeover time, start time and delivery date. Calculate the end time as start plus changeover plus quantity divided by speed, and let the next order on the same line start at that end time.

How do I calculate with hours and minutes in Excel?

Excel counts in days: an hour is 1/24 and a minute 1/1440. So divide production hours by 24 and a changeover in minutes by 1440 before you add them to a start time.

What is a digital planning board?

A digital planning board shows the production plan as a timeline per line, on which you drag orders. It takes orders from the ERP and progress from the floor, so the office and the floor see the same current plan.

Can I keep using Excel next to a planning board?

Yes. Frontlink reads in your current planning sheet at the start and exports the plan to Excel for anyone who wants it. The sheet is then a view, no longer the source.